The BUBBLES consortium has structured the work programme in 8 Work Packages (WP), combining research, project management and contribution to early standardisation activities, as shown in figure below.

WP 1 - Project management & coordination

Lead: UPV

Participants: UC - UNIROMA1 - EUROCONTROL - INDRA

Objective: To coordinate the work between the partners of the BUBBLES project and provide the liaison between the project management board and the SESAR JU to facilitate the technical and financial monitoring and assessment.

Work package description

This work package comprises all the activities conducted by the consortium to ensure the timely and effective execution of the work planned in the project and to coordinate the action of the consortium with SESAR JU activities and with sibling projects. This WP also includes all the tasks that will be needed to support the assessment of the expected V1 gate maturity level of the BUBBLES concept. Moreover, this WP is in charge of dealing with events that can arise during the execution of the project through an appropriate risk management policy.

Deliverable list:

D1.1. Minutes of the consortium meetings

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 10/2022

Download document: D1.1 Minutes of the consortium meetings


D1.2 Project Management Plan

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 06/2020

Download document: D1.2 Project Management Plan


D1.3 Progress reports

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 30/2022

Download document: D1.3 Progress reports


D1.4 V1 final data pack

Type: Report
Dissemination level: Public
Due date (month/year): 30/2022


D1.5 Final Project Report

Type: Report
Dissemination level: Public
Due date (month/year): 08/2022

WP2 - Concept definition & refinement

Lead: UPV

Participants: EUROCONTROL - INDRA

Objective: To formulate and refine a concept of a U-Space Separation Management service.

Work package description

This work package focuses on the formulation and refinement of a risk based, operation centric Concept of Operations (ConOps) for the separation management in the U-space. This WP deals with the definition of procedures to designate a separator, to assign separation minima and methods and to define the intervention fuction for UAS operating in the U-space.

Deliverable list

D2.1 Concept Formulation

Type: Report
Dissemination level: Public
Due date (month/year): 05/2022

Download document: D2.1 Concept Formulation 

WP3 - ConOps definition & classification

Lead: EUROCONTROL

Participants: UPV - INDRA

Objective: To identify a set of generic ConOps for UAS operations, classifying them based on a risk assessment.

Work package description

This work package defines and classifies detailed ConOps according to risk levels obtained using SORA methodology,  covering all the factors that can affect to their classification, and defines how this information shall be stored and organised.

Deliverable list

D3.1 Catalogue of generic ConOps

Type: Other
Dissemination level: Public
Due date (month/year): 11/2020

Download document: D3.1 Catalogue of Generic ConOps

WP4 - Separation minima & methods

Lead: UNIROMA1

Participants: UPV

Objective: To develop and validate algorithms to set separation minima and criteria to assign separation methods.

Work package description

This work package targets at developing and validating algorithms to set separation minima and criteria to assign separation methods and generate separation instructions when necessary. This work package will use a two step approach: first, to obtain the frequency of conflicts within an airspace volume taking into account the expected traffic density and missions and second, to compute the probability of collision in case of pair-wise conflicts.

Deliverable list

D4.1 Algorithms for analysing the collision risk

Type: Report
Dissemination level: Public
Due date (month/year): 11/2020

Download document: D4.1 Algorithms for analysing the collision risk 


D4.2 Guidelines to implement separation minima & methods.

Type: Report
Dissemination level: Public
Due date (month/year): 12/2020

Download document: D4.2 Guidelines to implement separation minima and methods

WP5 - Concept validation

Lead: INDRA

Participants: UPV - UC - UNIROMA1 -EUROCONTROL

Objective: To validate the proposed concept by means of a proof-of-concept.

Work package description

This work package deals with the validation of the BUBBLES concept using a proof-of-concept organised in 2 steps. To this purpose, the WP team will use a mock-up made of two segments: an air segment (UAS) and a ground segment (a web based platform that will be the access point to the required U-space services). The mock-up will include a communication system providing a ‘testable’ communication service (i.e. providing a service level specified in term of performance metrics). It is worth to highlight that only those features strictly needed to support the validation of the concept will be implemented. In both steps, UAS flight trials will be conducted in a ‘laboratory like’ environment (test sites in segregated air-space). The UAS will execute representative missions and will access the U-space management service through the web based platform. In the Step I, several AI algorithms will be tested against the corresponding SPR. In the Step II, the CNS performance and the environment will be monitored. Intentional perturbations to the CNS, as well as alterations to the Electromagnetic Environment, will be introduced and the separation minima and methods will be tuned to preserve safety under these conditions.

Deliverable list

D5.1 Concept Validation Test Plan (CVALP)

Type: Report
Dissemination level: Public
Due date (month/year): 04/2022

Download document: D5.1 Concept Validation Test Plan (CVALP) 


D5.2 Availability note for BUBBLES mockup

Type: Report
Dissemination level: Public
Due date (month/year): 04/2022

Download document: D5.2 Availability note for BUBBLES mock-up 


D5.3 Mock-up for the BUBBLES concept validation

Type: Demostrator
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 04/2022

Download document: D5.3 Mock-up for the BUBBLES concept validation


D5.4 Exploratory Research Validation Report

Type: Report
Dissemination level: Public
Due date (month/year): 05/2022

Download document: D5.4 Exploratory Research Validation Report 


D5.5 TRLA3

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 05/2022

Download document: D5.5 TRLA3

WP6 - Safety, Performance and Interoperability

Lead: EUROCONTROL

Participants: UPV - UC -UNIROMA1 - INDRA

Objective: To define set of generic OSEDs where the U-space Separation Management service will be provided and will draft both SPR and INTEROP supporting the provision of separation minima and methods in the U-space.

Work package description

This Work Package aims at adapting the performance-based approach use in manned aviation to develop safety and performance standards to the particularities of the U-space. This approach will be used to draft requirements for the systems supporting the separation management. These requirements will be attached to a set of generic OSED that will be defined so that they cover all the generic ConOps identified in previous WP.

Deliverable list

D6.1 Catalogue of generic OSED

Type: Other
Dissemination level: Public
Due date (month/year): 04/2021

Download document: D6.5 SPR-INTEROP-OSED 


D6.2 Required Performance specification for UAS PBx

Type: Report
Dissemination level: Public
Due date (month/year): 04/2021

Download document: D6.5 SPR-INTEROP-OSED 


D6.3 SPR & Implementation Guidelines for the AI separation systems

Type: Report
Dissemination level: Public
Due date (month/year): 04/2021

Download document: D6.5 SPR-INTEROP-OSED 


D6.4 SPR for weather and geospatial information systems.

Type: Report
Dissemination level: Public
Due date (month/year): 04/2021

Download document: D6.5 SPR-INTEROP-OSED 


D6.5 INTEROP requirements

Type: Report
Dissemination level: Public
Due date (month/year): 05/2022

Download document: D6.5 SPR-INTEROP-OSED 

WP7 - Performance monitoring

Lead: UC

Participants: UPV -INDRA

Objective: To develop tools implementing Communication and Surveillance Performance Monitoring methods.

Work package description

This work package deals with the development and validation of specifications for the monitoring tools required to assess the compliance of the CNS supporting the provision of the U-space Separation Management service within the framework of PCBS.

Deliverable list

D7.1 Availability note for the xPM Tool

Type: Report
Dissemination level: Public
Due date (month/year): 10/2021

Download document: D7.1 Availability note for the xPM Tool 


D7.2 CPM Tool

Type: Demostrator
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 10/2021

Download document: D7.2 CPM Tool


D7.3 SPM Tool

Type: Demostrator
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 10/2021

Download document: D7.3 SPM Tool

WP8 - Communication, dissemination & exploitation

Lead: INDRA

Participants: UPV - UC - UNIROMA1 - EUROCONTROL

Objective: To maximize the impact of the results of the project in the target audiences.

Work package description

This Work Package targets the communication, dissemination and exploitation of the results of the project, with emphasis in contributing to promote the social acceptance of the UAS technology and applications.

Deliverable list

D8.1 Data Management Plan

Type: ORDP (Open Research Data Pilot)
Dissemination level: Public
Due date (month/year): 10/2020

Download document:  D8.1 Data Management Plan


D8.2 Dissemination, Communication and Exploitation Plan

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 10/2020

Download document: D8.2 Project Communication, Dissemination and Exploitation Plan


D8.3 Dissemination, Communication and Exploitation Evaluation Report

Type: Report
Dissemination level: Confidential, only for members of the consortium (including the Commission Services)
Due date (month/year): 10/2022

Download document: D8.3 Dissemination, Communication and Exploitation Evaluation Report